通(tong)訊員(yuan)張妍 中國(guo)工業(ye)報(bao)記者 由慶祝(zhu)
當地時間2016年(nian)(nian)10月(yue)3日,哈電(dian)集團哈爾(er)濱電(dian)氣國(guo)際工程有限責任公司承建(jian)(jian)的厄瓜多爾(er)500KV超高壓(ya)輸變電(dian)項目C系(xi)統(tong)(tong)A7標段B回(hui)132km的500kV輸電(dian)線路(lu)、El INGA 500kV變電(dian)站的C系(xi)統(tong)(tong)間隔、SanRafael 500kV變電(dian)站的C系(xi)統(tong)(tong)間隔正式(shi)(shi)成功送電(dian)。標志(zhi)著哈電(dian)國(guo)際工程建(jian)(jian)設人員經過三年(nian)(nian)的不懈努力,繼(ji)今年(nian)(nian)上半年(nian)(nian)正式(shi)(shi)投運(yun)B系(xi)統(tong)(tong)和投運(yun)A系(xi)統(tong)(tong)之后(hou),“中(zhong)國(guo)制造”取(qu)得的又(you)一(yi)重(zhong)大里程碑成果。
據介(jie)紹,厄(e)(e)瓜多(duo)爾500kV超高壓(ya)輸變電(dian)項(xiang)目(mu)是哈電(dian)國(guo)際(ji)與(yu)厄(e)(e)瓜多(duo)爾國(guo)家電(dian)力公司(CELEC EP)簽(qian)訂(ding)的(de)總承包以(yi)及500kV輸變電(dian)系統運行(xing)維護合同。工(gong)作范圍包括科研、設計、供貨、施工(gong)、調(diao)試、試運行(xing),以(yi)及500kV系統的(de)運行(xing)維護。
該(gai)項目總工(gong)期的EPC部分為(wei)1185天(tian),運行維護部分為(wei)EPC之后的730天(tian)。500kV超(chao)高(gao)壓輸變電(dian)項目C系統從原(yuan)始森(sen)林(lin)(lin)出發穿(chuan)越安第斯山脈抵達(da)厄瓜多爾首(shou)都基多,在平原(yuan)區間穿(chuan)越原(yuan)始森(sen)林(lin)(lin)的無人區沼澤,進入高(gao)原(yuan)區間挑戰(zhan)最高(gao)海拔4252米的凍土。
為了(le)給業(ye)(ye)主提供高(gao)(gao)效、優質的(de)輸變電工(gong)(gong)(gong)程,自2013年7月26日項(xiang)目生效以來,哈(ha)電國際工(gong)(gong)(gong)程建設人員積極配(pei)合業(ye)(ye)主,保(bao)持緊密的(de)溝通,科學(xue)制(zhi)定(ding)工(gong)(gong)(gong)作計(ji)(ji)劃,合理分配(pei)施(shi)工(gong)(gong)(gong)作業(ye)(ye)資源,組織各級人員全(quan)力滿足設計(ji)(ji)、施(shi)工(gong)(gong)(gong)、安健環(huan)的(de)高(gao)(gao)標準要求,克服作業(ye)(ye)面復雜多變,常年暴雨、平原(yuan)(yuan)(yuan)與高(gao)(gao)原(yuan)(yuan)(yuan)交界地帶常年大霧等(deng)給工(gong)(gong)(gong)程建設帶來的(de)不利(li)影(ying)響,相(xiang)繼針對原(yuan)(yuan)(yuan)始(shi)森(sen)林熱帶雨林性質制(zhi)定(ding)了(le)雨季施(shi)工(gong)(gong)(gong)專(zhuan)項(xiang)方案,針對高(gao)(gao)原(yuan)(yuan)(yuan)凍土帶制(zhi)定(ding)了(le)高(gao)(gao)原(yuan)(yuan)(yuan)施(shi)工(gong)(gong)(gong)專(zhuan)項(xiang)措施(shi),針對雨林區域和(he)高(gao)(gao)原(yuan)(yuan)(yuan)區域極其(qi)惡劣、無(wu)法順利(li)施(shi)工(gong)(gong)(gong)的(de)地貌(mao)采取微樁基(ji)礎作業(ye)(ye),確保(bao)了(le)項(xiang)目施(shi)工(gong)(gong)(gong)的(de)連續性。
該項(xiang)目(mu)經過一系列超(chao)常(chang)規的(de)設(she)計方式、施(shi)(shi)工方式的(de)施(shi)(shi)工建設(she),哈電(dian)(dian)國際工程項(xiang)目(mu)部勝(sheng)利完成了500kV超(chao)高壓輸(shu)變電(dian)(dian)項(xiang)目(mu)C系統(tong)送(song)(song)電(dian)(dian),為厄(e)瓜(gua)多爾最(zui)大的(de)發電(dian)(dian)項(xiang)目(mu)Coca Codo Sinclair水電(dian)(dian)廠送(song)(song)出了電(dian)(dian)能(neng)。
據悉,500kV超高(gao)壓(ya)輸變電(dian)項目的(de)順利實施,使厄瓜多爾(er)擁有(you)500kV國家級骨干網(wang)。該(gai)項目建(jian)成后,承擔了厄瓜多爾(er)最大的(de)兩個水電(dian)站的(de)電(dian)能送出,實現了厄瓜多爾(er)全面推(tui)廣并(bing)實施清潔能源的(de)目標。
圖為哈(ha)電(dian)國際承(cheng)建的厄瓜多爾500kV輸變電(dian)項目一瞥。